Brettenham House strip-out / soft-strip project in London, United Kingdom by General Demolition
Strip-Out / Soft-Strip case study

Brettenham House

Helical / Third London Wall / Core Five

Strip-Out / Soft-Strip
Delivered by General Demolition
Client Helical / Third London Wall / Core Five
Completed 2024
Location London, United Kingdom
01

Project overview

The Brettenham House project involved the revitalisation of a historic structure located at 2-19 Lancaster Place, London, executed by General Demolition over a duration of 26 weeks. The scope included the removal of hazardous materials like asbestos and lead paint, along with the dismantling of non-structural elements while preserving 1930s marble facings and managing external windows for efficient waste disposal. The project required careful consideration due to its location in a bustling area, necessitating noise reduction strategies and community engagement to minimise disruption to neighbouring offices, including King Charles III's Duchy of Lancaster office.